我公司承建的云南省昆明市嵩明生活垃圾焚燒發電項目煙氣凈化工程于2023年11月28日通過72+24小時試運行。 The flue gas cleaning project of Songming Municipal Solid Waste Incineration Power Generation Project in Kunming, Yunnan Province, undertaken by our company, passed a 72+24-hour trial operation on November 28, 2023.
該項目建設一座焚燒處理1×500t/d的生活垃圾焚燒發電廠,配置1×500t/d機械爐排垃圾焚燒鍋爐+1×12MW汽輪發電機組。煙氣處理采用“SNCR脫硝+旋轉噴霧半干法脫酸系統+干法脫酸+活性炭噴射系統+袋式除塵器+飛灰輸送、存儲及穩定化工藝”的煙氣凈化工藝,為我司設備供貨工程。 The project aims to construct a 1 × 500t/d domestic waste incineration power plant, equipped with 1 × 500t/d mechanical grate waste incineration boiler and 1 × 12MW steam turbine generator set. The flue gas cleaning process of "SNCR denitration+rotary spray semi dry deacidification system+dry deacidification+activated carbon injection system+bag filter+fly ash transportation, storage and stabilization process" is adopted for flue gas treatment, which is our equipment supply project.
華星東方在云南省的業績涵蓋包括:曲靖、玉溪江川通海華寧、臨滄耿馬、紅河哈尼族彝族自治州、紅河哈尼族彝族自治州建水、昆明嵩明、昆明西山、昆明五華、西雙版納傣族自治州景洪、文山壯族苗族自治州硯山、文山壯族苗族自治州西疇、麗江等多個項目。 Huaxing East Co.'s performance in Yunnan Province includes multiple projects such as Qujing, Yuxi Jiangchuan Tonghai Huaning, Lincang Gengma, Honghe Hani and Yi Autonomous Prefecture, Honghe Hani and Yi Autonomous Prefecture Jianshui, Kunming Songming, Kunming Xishan, Kunming Wuhua, Xishuangbanna Dai Autonomous Prefecture Jinghong, Wenshan Zhuang and Miao Autonomous Prefecture Yanshan, Wenshan Zhuang and Miao Autonomous Prefecture Xichou, Lijiang, etc.